We are currently using the burnup schedule in Greenhopper in the "Number of Errors" mode. Currently, only standard types of problems (errors, tasks, histories) are taken into account in the calculation of combustion.
Question: Is there an opportunity to consider also subtasks in the calculation of combustion?
Example:
Assume we have 3 stories and 8 subtasks associated with them. If I close the story, this will affect the overtaking chart. But if I close the subtask, the chart will not be affected.
I checked the project filter, which also includes subtasks. But for some reason they are not considered on the charts (which is bad for us).